Traffic & Construction
Construction timeline, truck routes, hours of operation, and dust/noise mitigation during construction.
This page follows our Community Right-to-Know commitment
What we knowWhat we're still studyingWhat you can influence
What We Know
Construction Timeline
We expect the construction phase to last approximately 12–18 months. Major phases include:
- Site preparation: clearing, grading, and building stormwater infrastructure (2–3 months)
- Civil construction: pouring foundations, constructing access roads, and laying underground conduit (3–4 months)
- Equipment delivery and installation: delivering and installing Megapack units, inverters, and transformers (4–6 months)
- Electrical interconnection: connecting the system to the Carpenter Hill 115 kV substation (2–3 months)
- Testing and commissioning: testing the system before starting commercial operation (1–2 months)
Truck Routes
Construction will require delivery of 136 Tesla Megapack 3 units and associated equipment. We are planning truck routes to:
- Use state highways and major roads as much as possible
- Minimize travel through residential neighborhoods
- Coordinate with the Charlton Police Department and Highway Department on traffic management
- Schedule oversize loads during off-peak hours when feasible
Hours of Operation
Construction activities will follow Charlton's standard construction hours:
- Monday–Friday: 7:00 AM – 5:00 PM
- Saturday: 8:00 AM – 3:00 PM (if needed)
- Sundays and holidays: No construction
During Construction Mitigation
We're committed to being a responsible neighbor during construction:
- Dust control: we will use water trucks and stabilized construction entrances to minimize dust
- Noise management: we will maintain equipment with proper mufflers and prevent unnecessary idling
- Road maintenance: we will regularly sweep public roads near the site entrance
- Erosion control: we will install silt fencing, hay bales, and stabilization measures throughout construction
What We're Still Studying
- Final truck route plan: we will finalize the truck route plan after coordinating with town departments
- Traffic impact analysis: we will analyze and quantify the volume and timing of construction traffic
- Emergency vehicle access: we will ensure construction activities do not impede emergency response
What You Can Influence
- Route preferences: tell us which roads you prefer construction traffic to avoid
- Construction hour concerns: let us know if the proposed hours cause problems for your neighborhood
- Communication preferences: tell us if you want advance notice of heavy delivery days through Share Your Voice