Traffic & Construction

Construction timeline, truck routes, hours of operation, and dust/noise mitigation during construction.

This page follows our Community Right-to-Know commitment

What we knowWhat we're still studyingWhat you can influence

What We Know

Construction Timeline

We expect the construction phase to last approximately 12–18 months. Major phases include:

  1. Site preparation: clearing, grading, and building stormwater infrastructure (2–3 months)
  2. Civil construction: pouring foundations, constructing access roads, and laying underground conduit (3–4 months)
  3. Equipment delivery and installation: delivering and installing Megapack units, inverters, and transformers (4–6 months)
  4. Electrical interconnection: connecting the system to the Carpenter Hill 115 kV substation (2–3 months)
  5. Testing and commissioning: testing the system before starting commercial operation (1–2 months)

Truck Routes

Construction will require delivery of 136 Tesla Megapack 3 units and associated equipment. We are planning truck routes to:

  • Use state highways and major roads as much as possible
  • Minimize travel through residential neighborhoods
  • Coordinate with the Charlton Police Department and Highway Department on traffic management
  • Schedule oversize loads during off-peak hours when feasible

Hours of Operation

Construction activities will follow Charlton's standard construction hours:

  • Monday–Friday: 7:00 AM – 5:00 PM
  • Saturday: 8:00 AM – 3:00 PM (if needed)
  • Sundays and holidays: No construction

During Construction Mitigation

We're committed to being a responsible neighbor during construction:

  • Dust control: we will use water trucks and stabilized construction entrances to minimize dust
  • Noise management: we will maintain equipment with proper mufflers and prevent unnecessary idling
  • Road maintenance: we will regularly sweep public roads near the site entrance
  • Erosion control: we will install silt fencing, hay bales, and stabilization measures throughout construction

What We're Still Studying

  • Final truck route plan: we will finalize the truck route plan after coordinating with town departments
  • Traffic impact analysis: we will analyze and quantify the volume and timing of construction traffic
  • Emergency vehicle access: we will ensure construction activities do not impede emergency response

What You Can Influence

  • Route preferences: tell us which roads you prefer construction traffic to avoid
  • Construction hour concerns: let us know if the proposed hours cause problems for your neighborhood
  • Communication preferences: tell us if you want advance notice of heavy delivery days through Share Your Voice