Question and Submission History

Original questions and earlier responses, linked to the consolidated answer bank.

Back to questions and answers

This history preserves the anonymized wording and earlier written responses in the imported project records. Earlier responses may describe a previous design or contain wording now under review. Use the linked consolidated question for the current response status.

A source record can contain several questions. These records are not a count of individual submissions or people. Original messages and dates are still being reconciled; this history does not establish that every project submission has been captured.

Showing 1 of 211 source records

Website and email · Submission date not confirmedWill blasting be needed, and could it affect my well?

Editor's note: there is a better, updated answer.

The response below is kept as a record of what was said at the time. It may describe an earlier design or wording that has since been corrected. Use the current answer instead:

Earlier written draft, not current (answers as of October 7, 2026)

Not yet answered in full. It has not been decided whether blasting is needed. There is ledge on both sides of the site, and the engineering that determines how much rock must be removed has not been published. Rock can sometimes be removed by hammering or ripping instead of blasting, and that choice is made in the construction plan. Blasting can send vibration through rock, and how far that matters depends on the amount of rock removed, the distance to a well, and the local geology. No study yet shows whether any well would be affected.

If blasting is used, these protections apply or are proposed:

  • State rules. Blasting in Massachusetts requires a permit from the local fire department under 527 CMR 1.00, a licensed blaster, and a blasting plan reviewed by the Fire Chief. Property owners within 250 feet of a blast must be offered a free pre-blast survey, and vibration is monitored with seismographs during blasting.
  • Draft Community Benefits Plan. The draft proposes testing private wells within 1,000 feet of the work limit, plus wells on T. Hall Road, at the project's cost before construction. Those wells would be tested again after any blasting near a well. If a test shows a change linked to the site, the project would pay for bottled water within 48 hours, then for treatment or a replacement well. The draft is not final.

Wells about a mile from the site are outside both distances. The hydrogeologic study and the well survey are meant to show which wells need to be part of this work, and their results are not published. If you rely on a private well, send us your road and we will check it against the site plans and the well records.

Update, November 18, 2026. This answer says the draft plan proposes bottled water within 48 hours. Separately, if oil or a hazardous material reached a drinking water well serving a home, Massachusetts cleanup rules presume that the immediate response must stop or reduce that exposure, and they list a temporary alternative water supply as one way to do it (310 CMR 40.0414). Those rules do not set a number of hours. The 48-hour timeline is the draft plan's own. An updated answer is now available: Will there be blasting, and could it affect my well?

How the issues were handled

A written response is recorded. Sending an individual reply, considering feedback, and making a design change require separate evidence.

  • Will there be blasting, and could it affect my well?
    Individual reply: not confirmed. Consideration: not recorded. Design change: not confirmed.